How to Bid a Plumbing Job: A Worked Example
A plumbing bid has to cover four things: the hours, the parts, anything you hire out, and enough on top to keep the doors open and make a profit. Miss one and you are working for free on part of the job. Before any bid, run your wage through the labor cost calculator so every hour is priced at what it really costs you. Below are the five steps, then one bid worked to the cent.
The example job: the plumbing for a new basement bath with a toilet, a sink and a shower. Rough-in and trim. The general contractor supplies the fixtures. Wage and payroll tax come from public sources; every other number is an example. Use your own.
Step 1: Walk the job and write the scope by phase
Write the scope the way you will work it: rough-in, then trim. List what is in (supply and drain lines, the shower valve, the drains) and what is out (fixtures supplied by others, drywall, tile). Say who supplies the fixtures in writing. A plumbing bid without a written scope turns every surprise into an argument, and the first one is usually who pays for the fixture the client changed their mind on. Price those as changes and track change orders as they happen.
Step 2: Price parts from a real supply-house quote
Price pipe, fittings, the valve and the drains from a quote you got for this job, dated the day you bid. Prices from memory are how bids go wrong. The example uses $1,850 of parts. Put a date on the bid so a price change at the supply house does not come out of your margin.
Two habits keep the parts line honest. First, add the small stuff on purpose: primer and cement, hangers, straps, test caps and the fittings you always end up needing one more of. Second, when the client has not picked a valve or a drain yet, write an allowance on the bid (a dollar amount for that part) and say that a different choice changes the price. An allowance is far better than a guess hidden inside your total.
Step 3: Build your loaded labor rate
The wage is the start, not the rate. For scale, the median wage for plumbers, pipefitters and steamfitters was $30.67 an hour in May 2025, according to the Bureau of Labor Statistics (read November 13, 2026). That is a national median wage, not a rate to charge. On top of it, the employer pays 6.2% Social Security and 1.45% Medicare, per IRS Topic 751: 7.65%. State unemployment and federal unemployment tax are not in the example; add yours.
| Input | Value | Source |
|---|---|---|
| Wage | $30.67 an hour | BLS median, May 2025 |
| Payroll taxes | 7.65% | IRS: 6.2% + 1.45% employer share |
| Workers' comp | 5% | Example: use your policy rate |
| Overhead per hour | $12 | Example |
| Non-billable share | 20% | Example |
| Burdened cost per paid hour | $46.55 | $30.67 x (1 + 7.65% + 5%) + $12 |
| Loaded cost per billable hour | $58.19 | $46.55 / (1 - 20%) |
The full method, with what goes in the overhead number, is in how to calculate labor cost.
Step 4: Count hours per phase from your own past jobs
There is no hours-per-fixture rule that fits every house: access, slab or framed floor, and how far you are from the stack change everything. Use your own past jobs, by phase. The example uses 16 hours of rough-in and 8 hours of trim.
If you do not have past hours by phase, start keeping them now. Every job you track makes the next bid closer to the truth.
Step 5: Add subs, permit and disposal, then markup
This job needs concrete saw cutting for the drain, hired out at $450. The permit and disposal come to $200 here; check your city's fee. (Some contractors put the permit on its own line at cost instead; either way, it must be in the bid.) Then add markup to cover the overhead that is not in the hourly rate, plus profit. The example uses 35%. That is not a standard: markup is on cost and margin is on price, so read markup vs margin before you pick yours, and know your construction overhead first.
The full worked example
Put the four lines into the free job cost calculator and it returns the same price and margin.
| Bid line | Amount |
|---|---|
| Labor: 24 hours x $58.19 | $1,396.56 |
| Materials (pipe, fittings, valve, drains) | $1,850.00 |
| Sub: concrete saw cutting | $450.00 |
| Other: permit and disposal | $200.00 |
| Total cost | $3,896.56 |
| Markup 35% | $1,363.80 |
| Bid price | $5,260.36 |
After you send it
Put the scope and the exclusions on the bid itself, not in a text message. A bid is a price you commit to for that scope; for how that differs from an estimate or a quote, see quote vs estimate vs bid. When the job is done, bill it on the contractor invoice template with the same lines you bid. Then compare what the job really cost against the bid. That comparison is what job costing is, and it is the only way your next bid gets better. More traps to avoid are in contractor bidding mistakes. For a trade where installs and service calls are costed after the bid, see how to job cost HVAC work.
Before you send it:
- Scope written by phase, with exclusions.
- Who supplies the fixtures, in writing.
- Parts priced from a dated quote.
- Permit and inspection trips counted.
- How changes will be priced, in writing.
Where the app fits (honest limits)
Step 4 only works if you know your real hours from past jobs. I built Job Cost Pro so those hours and the receipts land on each job while it runs: the crew clocks in so hours land at real cost, and you photograph receipts and the AI reads the line items (when the receipt names the job or you scan at the jobsite, it suggests that job for one tap to confirm). The margin you see is from costs recorded so far. It is not a scheduling tool. Free on the App Store: 3 jobs, 50 receipts a month, AI scanning included, no card. Get it here.
There is more on how the app tracks plumbing work on the plumbing job costing page.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
How do you bid a plumbing job?
Write the scope by phase, price parts from a supplier quote, multiply your hours by a loaded labor rate, add subs, permit and disposal, then add markup. In the example here, $3,896.56 of cost at a 35% markup bids at $5,260.36.
How do I figure my labor rate for a plumbing bid?
Take the wage, add payroll taxes, workers comp and overhead per hour, then divide by the share of paid hours you can bill. With a $30.67 wage, 7.65% payroll tax, 5% comp, $12 an hour of overhead and 20% non-billable time, the loaded rate is $58.19.
What markup should a plumber use?
There is no single standard. Pick a markup that covers the overhead your hourly rate does not carry plus the profit you want, and check the margin it gives: a 35% markup is a 25.9% gross margin.
Should the bid include the permit fee?
Yes. Look up your city fee for the job and put it in the bid, either in other costs or on its own line at cost.
What is the difference between a plumbing bid and an estimate?
A bid is a price you commit to for a written scope; an estimate is a rough idea of cost that can change.