How to Bid Electrical Jobs: A Worked Example
Most bidding advice for electricians is a list of tips. I wanted one job carried all the way from two people's wages to a price you can send, with every number shown. Run each person's wage through the labor cost calculator before you price a single hour. The rest of this post is that job, step by step.
- Walk the job and write the scope
Circuits, devices, fixtures, access, who supplies what.
- Price the materials
A supplier quote dated the day you bid.
- Price two rates
Licensed and helper hours, each at its own loaded cost.
- Add other costs
Consumables, dump, fuel. The permit goes on its own line.
- Add markup
Enough to cover overhead and leave profit.
- Stress test it
Price a failed inspection and a copper jump before you send it.
Walk the job and write the scope
The example job: wiring a basement finish of about 700 square feet. Six new circuits, 24 devices, 10 recessed lights. Every price below is an example input, not a market rate. Your supplier, your city and your crew will change every number.
On the walk, write down what the bid covers and what it does not: the circuits, the device count, the fixture count, how you get wire to the panel, any old wiring you will touch, and who supplies the light fixtures. That list is the bid. Anything not on it is a change order later, and a written scope is what makes that conversation easy instead of a fight.
Price the materials from a quote dated today
Price materials from a supplier quote on bid day, not from memory or last year's job. Copper moves, so put an expiry date on the bid and say so on the page. Pick a number of days and use it on every bid.
| Material (example prices) | Amount |
|---|---|
| Cable | $420 |
| Boxes and fittings | $160 |
| 6 breakers | $330 |
| Devices and plates | $190 |
| 10 LED recessed lights | $360 |
| Materials total | $1,460 |
Licensed and helper hours are two different rates
The most common hole I see in small-shop bids is one blended rate, or worse, the raw wage. A licensed electrician and a helper cost you different amounts per hour, and each one costs more than the wage. The loaded labor rate adds payroll taxes, workers' comp and overhead per hour, then divides by the share of paid hours you can actually bill.
For scale: the national median wage for electricians was $30.38 an hour in May 2025, according to the Bureau of Labor Statistics (read November 13, 2026). That is a wage, not a price to charge. The example uses its own inputs:
| Licensed | Helper | |
|---|---|---|
| Wage | $36.00 | $20.00 |
| Payroll taxes / comp | 10% / 5% | 10% / 5% |
| Overhead per hour | $6.60 | $6.60 |
| Burdened cost per paid hour | $48.00 | $29.60 |
| Non-billable share | 20% | 20% |
| Loaded cost per billable hour | $60.00 | $37.00 |
| Hours on this job | 16 (rough-in 7, trim 6, inspections 3) | 16 (rough-in 9, trim 7) |
| Job labor | $960.00 | $592.00 |
Two things to notice. Inspections are in the hours: three licensed hours for meeting the inspector. And the helper's loaded cost is $37, not $20. Labor comes to $1,552 for 32 hours, a blended $48.50 an hour, which is the number you type into a one-rate calculator. For one loaded rate worked step by step on a different trade, see how to bid a plumbing job.
Permits and other costs
Other costs are the small stuff that adds up: wire nuts, tape, staples, a dump run, fuel. This job carries $100. The permit is different: look up your city's fee schedule and put the permit on the bid as its own line, at cost, outside the marked-up total. That way the client sees exactly what the city charges and you never mark up a fee you did not set.
Markup covers overhead and profit
Your loaded rates already carry the overhead you can tie to an hour. Markup covers the rest of the overhead (the office, the phone, the insurance that does not change with hours) and leaves profit. Markup is figured on cost, margin on price, so a 40% markup is not a 40% margin. The post on markup vs margin explains the gap, and the overhead and profit calculator finds your own number from a year of books. The 40% below is an example, not a standard.
The worked example, start to finish
Put the totals in the job cost calculator to get price and margin in one step: 32 hours at $48.50, $1,460 in materials, no subs, $100 other, 40% markup.
| Bid line | Amount |
|---|---|
| Labor: 32 hours at a blended $48.50 | $1,552.00 |
| Materials | $1,460.00 |
| Other costs | $100.00 |
| Total cost | $3,112.00 |
| Markup 40% | $1,244.80 |
| Bid price | $4,356.80 |
| Permit (your city fee, at cost) | Own line |
That 28.6% is gross margin. It still has to pay the overhead that is not in the hourly rates, so it is not all profit. If your construction overhead runs high, the markup has to be higher than this example to leave anything.
Stress test the bid before you send it
A bid is a guess about the future. Before you send it, price two things that go wrong on electrical work all the time, with the price held at $4,356.80. A failed rough-in inspection adds two licensed hours ($120): cost goes to $3,232 and margin drops to 25.8%. Add $150 of copper price drift on top: cost $3,382, margin 22.4%.
If 22.4% still works for you, send it. If it does not, raise the price or tighten the scope now, not after the inspector leaves. More of these traps are in the post on bidding mistakes. And for scale: a smaller job, like the $3,600 panel upgrade on our electrical contractor page, follows the same math with fewer lines.
Before you send the bid:
- Scope is written and agreed, including who supplies fixtures.
- Material prices come from a quote with today's date.
- The permit fee is looked up and on its own line.
- Inspection trips are in the licensed hours.
- The bid has an expiry date.
Where the app fits (honest limits)
A bid is only as good as what you learn from the last job. I built Job Cost Pro so the real hours and receipts land on each job while it runs: you photograph receipts and the AI reads the line items (when the receipt names the job or you scan at the jobsite, it suggests that job for one tap to confirm), and the crew clocks in so hours land at real cost. Then the margin you see is from costs recorded so far, and your next bid starts from what the last one really cost. It is not a scheduling tool. Free on the App Store: 3 jobs, 50 receipts a month, AI scanning included, no card. Get it here.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
How do you bid an electrical job?
Write the scope, price materials from a dated supplier quote, price licensed and helper hours at each loaded rate, add other costs, then add a markup that covers overhead and profit. Put the permit on its own line at cost. In the example here, $3,112 of cost at a 40% markup bids at $4,356.80.
How many hours should I bid for an electrical job?
Use your own past jobs, split by phase: rough-in, trim and inspection trips. There is no rule number that fits every house. The example basement job uses 16 licensed hours (including 3 for inspections) and 16 helper hours.
Should I charge the same rate for a helper?
Price the cost separately, because a helper costs you less per hour than a licensed electrician. In the example the loaded cost is $60 an hour for the licensed electrician and $37 for the helper. How you show rates to the client is your choice; what matters is that the bid covers both costs.
How much should an electrician mark up a job?
Enough to cover the overhead your hourly rates do not carry, plus the profit you want. There is no single standard. Find your overhead from a year of books, then check the margin a markup gives you: a 40% markup is a 28.6% gross margin.
Do I include permit fees in my electrical bid?
Yes, but as their own line at the city fee, outside the marked-up total. Fees differ by city, so look up your city fee schedule for each job.