What Is an Allowance in Construction?
Allowances let you sign a job before every finish is chosen. They are also one of the quietest ways a remodeler loses money: the client upgrades, the crew installs it, and the difference never makes it onto an invoice. When an allowance runs over, the fix is a written change order before the work, not a surprise line at the end.
What an allowance covers (and what it does not)
An allowance covers a named item with a named dollar amount. The contract has to say what the amount pays for. There are two common kinds:
- Material only. The amount buys the tile, the faucet or the fixture. Your labor to install it is already in the price.
- Material and labor. The amount covers both. A harder install, like a large-format tile or a heavy fixture, can push it over even when the material price looks fine.
If the contract does not say which kind it is, you will find out during the job, in an argument. Write it next to every allowance line.
Allowance vs contingency
They sound alike and work differently. An allowance is a known item with an unknown pick: everyone knows there will be tile, nobody has chosen it. A contingency is money for a problem nobody can name yet, like rot behind a wall. Keep them on separate lines in the bid and in the budget, so a client never reads an allowance as spare money, and so you never spend contingency to cover an upgrade the client chose.
| Allowance | Contingency | |
|---|---|---|
| What it is for | A known item not picked yet | A problem nobody can name yet |
| Example | Tile, faucets, light fixtures | Rot, hidden wiring, a bad subfloor |
| If it runs over | Client pays the overage (change order) | Depends on the contract |
| If it runs under | Client gets a credit | Depends on the contract |
How to set an allowance amount
Price the allowance from a real item, not a round number you hope is enough. Pick a mid-range option that fits what the client told you they like, price it from your supplier, and write down which item you priced. Then the client can see what the amount buys before they shop.
There is no standard allowance amount or percent that fits every job, and anyone who gives you one without knowing the house and the client is guessing. A low allowance wins the bid and starts the job with a change order already coming. A fair one keeps the conversation calm when the client picks.
Overages and credits: a worked example
These are example numbers. Your contract decides the markup, if any, on an overage.
| Case | Allowance | Client pick | Difference | What happens |
|---|---|---|---|---|
| Client picks up | $3,000 | $4,200 | $1,200 over | Change order: $1,380 with a 15% markup |
| Client picks down | $3,000 | $2,400 | $600 under | Credit to the client: $600 |
Whatever the markup is, it should be written in the contract before the job starts. A markup that shows up for the first time on a change order feels like a penalty to the client, even when it is fair.
How allowances leak profit
- The overage never gets billed. The client picks the $4,200 tile, the crew sets it, and nobody writes the $1,200 down. It comes out of your margin.
- The labor is not adjusted. A material-only allowance does not cover the extra hours a harder install takes.
- The pick comes late. The crew waits or moves to another task, and the schedule slips while the allowance sits open.
The fix is boring and it works: keep every allowance on its own line in your job budget, set a date for each pick, and close each line with a change order or a credit. If you track costs by job, this shows up in how you track job profitability: an allowance line that is over and not billed is margin you already gave away.
Allowances on cost-plus and fixed-price jobs
On a fixed-price job, the allowance is the one part of the price that can still move, so the overage math above matters most there. On a cost-plus job, the client pays real costs anyway, but an allowance line still tells them what you expected the item to cost, so a big pick does not look like a surprise. For how the two contract types differ, see fixed price vs cost plus contracts, and for billing a cost-plus job, see cost-plus invoicing.
If the client has not picked yet when you write the scope, name the allowance in the scope too. See how to write a construction scope of work.
Where the app fits (honest limits)
In Job Cost Pro, a cost-plus job can import its budget from a cost sheet, and a section the sheet marks as an allowance gets an Allowance tag before you apply it, so it stays its own line. Change orders adjust the job's effective contract amount, and the margin is shown from costs recorded so far. It does not watch your allowances for you: closing each one is still your call. Free on the App Store: 3 jobs, 50 receipts a month, AI scanning included, no card. Get it here.
When an allowance does run over, start from the free change order template.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
What is an allowance in a construction contract?
It is a dollar amount for an item the client has not picked yet, like tile or fixtures. If the final pick costs more, the client pays the overage, usually by change order. If it costs less, the client gets a credit.
Who pays if an allowance goes over?
Usually the client, through a change order, because the allowance was the agreed amount for that item. The contract should say how the overage is figured, at cost or with a markup, before the job starts.
Do contractors mark up allowance overages?
Some do and some bill the overage at cost. It depends on the contract. The worked example on this page uses a 15% markup only as an example input: a $1,200 overage becomes a $1,380 change order.
What is the difference between an allowance and a contingency?
An allowance is for a known item that has not been picked, like tile. A contingency is for a problem nobody can name yet, like rot behind a wall. Keep them on separate lines in the bid and the budget.
How do I set an allowance amount?
Price a real mid-range item that fits what the client told you they like, write down which item you priced, and say whether the amount covers material only or material and labor. There is no standard amount that fits every job.
What happens if the client picks something cheaper than the allowance?
The client gets a credit for the difference. In the example on this page, a $3,000 tile allowance with a $2,400 pick gives a $600 credit.