T&M Billing Example With a Not-to-Exceed Cap
Time and materials sounds simple until you sit down to send the first bill. How many lines? Do you show the markup? What happens when the job creeps toward the cap you agreed to? I would rather show you than tell you, so this post walks one job from the agreement to the second invoice with every number filled in. Every number below fits on the free time and materials invoice template, which has a labor table, a materials table and a receipts-attached checkbox.
The job is made up, and so are the rates. Use your own. Where a point is a contract choice (the cap, the notice, the markup), I say so: word those with your attorney.
The job and the agreement
A water-damage repair in a hall bath and the wall behind it. Nobody can see inside that wall until it is open, so a fixed price would be a guess. T&M is the honest way to price it. Here is what the client and I agreed to in writing:
- Rates
Lead carpenter at $65 an hour, helper at $45 an hour.
- Materials
Billed at receipt cost plus a 15% markup.
- Invoices
One every week, with the receipts attached.
- Cap
A not-to-exceed cap of $6,000 for the whole job.
- Notice
Written notice to the client when billing passes 75% of the cap ($4,500).
The cap protects the client from an open checkbook. The 75% notice protects me from a surprise conversation at the end. Both are choices we made for this job, not rules that come with T&M. If you want the bigger picture of when T&M fits and when a fixed price is better, read fixed-price vs cost-plus contracts.
Where the $65 rate comes from
A T&M rate that only covers the wage loses money on every hour. Before you set one, find your true cost per billable hour. For the lead in this example: $30 an hour wage, 10% payroll taxes, 8% workers' comp, $6 an hour of overhead, and 15% of paid hours that cannot be billed (drive time, pickup runs, cleanup).
| Step | Math | Result |
|---|---|---|
| Burdened cost per paid hour | $30 x (1 + 10% + 8%) + $6 | $41.40 |
| True cost per billable hour | $41.40 / (1 - 15%) | $48.71 |
| Billing rate | Agreed with the client | $65.00 |
| Left per billable hour | $65.00 - $48.71 | $16.29 |
Plug your own wage and costs into the labor cost calculator to see your true cost per billable hour before you set a T&M rate. If the rate you can get is barely above that number, T&M will not save the job.
Invoice 1, line by line
Week one: demo, a moisture check, new drywall hung, tape and mud started.
| Day | Who | Work | Hours | Rate | Amount |
|---|---|---|---|---|---|
| Mon | Lead | Demo wet drywall and insulation | 8 | $65 | $520.00 |
| Mon | Helper | Demo and haul-out | 8 | $45 | $360.00 |
| Tue | Lead | Moisture check and photos | 3 | $65 | $195.00 |
| Wed | Lead | Hang drywall | 7 | $65 | $455.00 |
| Wed | Helper | Hang drywall | 7 | $45 | $315.00 |
| Thu | Lead | Tape and mud | 6 | $65 | $390.00 |
| Labor | 24 lead + 15 helper hours | 39 | $2,235.00 |
| Item | Receipt cost | Markup 15% | Billed |
|---|---|---|---|
| Drywall and screws | $412.38 | $61.86 | $474.24 |
| Joint compound and tape | $86.42 | $12.96 | $99.38 |
| Dumpster fee | $275.00 | $41.25 | $316.25 |
| Dehumidifier rental | $180.00 | $27.00 | $207.00 |
| Materials | $953.80 | $143.07 | $1,096.87 |
Invoice 1 total: $2,235.00 of labor plus $1,096.87 of materials = $3,331.87. Every materials line has its receipt behind it. On a T&M job the receipts are the proof, and a client who can check the math has less to argue about. One thing I left off on purpose: sales tax. Whether it applies to materials or labor on repair work depends on your state, so check your state's rule before you add a tax line.
You can grab the same layout as a spreadsheet: download the time and materials invoice (.xlsx). It has no cap line, so add one by hand if your contract has a cap.
Why 15% markup is not 15% profit
Markup is figured on cost. Margin is figured on the price. On the materials above, the $143.07 of markup is 15% of the $953.80 cost, but only 13.0% of the $1,096.87 billed. The markup calculator shows the same 15% markup as a 13.0% margin. And that 13.0% is before the time someone spent driving to buy it, carrying it and handling the return. If the difference still trips you up, the post on markup vs margin walks through it.
How much markup to put on T&M materials is whatever your agreement says. Pick it on purpose, write it in the contract, and show it on the invoice so nobody feels it was hidden.
Tracking billed-to-date against the cap
A cap only works if you watch it every invoice, not at the end. Add a small block to the bottom of each invoice: the cap, billed so far, the percent used, and what is left.
| After | Billed to date | % of $6,000 cap | Left under the cap |
|---|---|---|---|
| Invoice 1 | $3,331.87 | 55.5% | $2,668.13 |
| Invoice 2 | $4,686.78 | 78.1% | $1,313.22 |
After invoice 1 the job is at 55.5% of the cap with the wall closed up. That is where it should be. The next week tells you whether the cap holds.
Invoice 2 and the cap notice
Week two: sand, prime and paint, and new baseboard.
| Line | Math | Amount |
|---|---|---|
| Lead: sand | 5 hours x $65 | $325.00 |
| Lead: paint | 7 hours x $65 | $455.00 |
| Helper: paint | 6 hours x $45 | $270.00 |
| Primer and paint | $168.94 x 1.15 | $194.28 |
| Baseboard | $96.20 x 1.15 | $110.63 |
| Invoice 2 total | $1,050.00 labor + $304.91 materials | $1,354.91 |
Invoice 2 puts the job at $4,686.78, 78.1% of the cap. That passes the 75% line, so the written notice goes out with this invoice. Here is why it matters: the trim, the vanity reset and the touch-up I still see will take about $1,600 more. That would bring the job to $6,286.78, which is $286.78 over the cap.
So I stop before I pass the cap, not after. Going past a cap without a signed change is the fastest way to work for free. It is the same rule as any other change, and the post on how to track a change order covers the paperwork. The rest of the invoice basics (terms, due dates, what to put at the top) are in how to write a contractor invoice.
Where the app fits (honest limits)
On T&M the hours and the receipts are the invoice, so they have to be right. That is the part I built Job Cost Pro for: the crew clocks in so hours land on the job, and you photograph each receipt as you buy it; the AI reads the line items, and when the receipt names the job or you scan at the jobsite it suggests that job for one tap to confirm. An invoice starts from the job, with the receipts and labor you mark to bill back, and you review it before it goes out. Be clear on what it does not do: it does not watch a not-to-exceed cap and it does not add a materials markup for you, so the cap block and the markup stay your job. It is not a scheduling tool. Free on the App Store: 3 jobs, 50 receipts a month, AI scanning included, no card. Get it here.
For cost-plus work, where the client pays your actual costs plus a fee, the billing works a little differently; there is a page on cost-plus invoicing for that.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
How do you calculate a time and materials bill?
Multiply the hours by the agreed rate for each person, then add materials at their receipt cost times one plus the agreed markup. In the example here, 24 lead hours at $65 and 15 helper hours at $45 is $2,235, and $953.80 of materials at a 15% markup bills $1,096.87, for an invoice of $3,331.87.
What does not-to-exceed mean on a T&M job?
It is a cap the client and contractor agree to: the total bill for the agreed work will not go above that number unless both sides approve more in writing. It gives the client a ceiling while you still bill real hours and real materials.
What happens if a T&M job goes over the not-to-exceed amount?
It depends on your contract, so get the answer in writing before the job starts. The safe habit is to warn the client before you reach the cap, show the reason and the number, and get a signed change before you do work past it. Ask your attorney how to word the cap and the notice.
How much markup do contractors put on T&M materials?
Whatever the agreement says. There is no single right number. Pick a markup that covers the time spent buying, hauling and handling materials, write it into the contract, and show it on each invoice. The example in this post uses 15%.
Is a 15% markup the same as 15% profit?
No. Markup is a percent of cost and margin is a percent of price. A 15% markup on $953.80 of materials is $143.07, which is only 13.0% of the $1,096.87 billed, and that is before the time spent getting the materials.