How to Handle Material Price Increases on Fixed-Price Jobs

You are about to order cabinets for a fixed-price remodel. The supplier sends a new quote, and the package costs more than it did when you priced the job. The client's scope is the same. You still have to decide what to order, what the new cost does to the job, and what belongs in a talk with the client. To add up one job from its parts, the free job cost calculator shows the price, the profit and the margin.

Start with the supplier's new quote
- Compare like for like
Same quantities, grades, sizes, finishes, delivery and tax. Find which part moved: the quantity, a delivery charge or the unit price.
- Ask the supplier
How long the new quote is good for, what is in stock, and when it could arrive.
- Check what is already ordered
Ask which price applies to orders and deposits you already placed, and get the answer in writing.
- Save both quotes
Note the order deadline. If you check another supplier, compare the full delivered cost and lead time.
If another material would change the finish, the install or the schedule, show those differences to the client before you swap anything. Focus the new numbers on the quantities still open to a price change.
Check the signed scope before you talk price
Read the signed scope, the selections, the allowances and the process for changes. Look for any terms about material prices and who approves a change. Those terms guide what you talk about with the client. Use the signed paperwork to check any change to what you bill.
If you need to talk with the client, show the first selection, the new supplier quote and the date you need a decision. Explain the options you can really offer: keep the specified material, wait longer for it, or pick another product. Say what each one does to the scope and the schedule, and follow the agreed approval steps before you order a swap or start extra work. See fixed price vs. cost plus contracts.
Update your job cost forecast
Keep the first estimate as your starting point. For each line the price hit, keep the first budget, the costs recorded so far and the cost to finish in separate columns. When a charge is recorded, it replaces the estimate for the part it covers. Recorded costs plus the updated cost to finish is the forecast. Check open orders for amounts you already counted.
Look at the whole job after you change the material line. A swap can also change labor, freight, disposal or install supplies. Put a date on each forecast and write down what you will check again next week. The margin can move again as more costs come in.
Fictional worked example
When the cabinets arrive, you record them with $11,000 of other direct costs already spent: $20,400 recorded so far, with $13,000 of the other costs still to come. Later the owner signs a separate $2,000 change order for pantry shelving that you expect to cost you $1,200. Keep it on its own line, so the reason for the higher price stays clear.
| Line | Amount |
|---|---|
| Signed value ($40,000 + $2,000) | $42,000 |
| Direct costs recorded so far | $20,400 |
| Direct costs still ahead ($13,000 + $1,200) | $14,200 |
| Projected direct costs | $34,600 |
| Projected gross profit ($42,000 - $34,600) | $7,400 |
| Projected gross margin ($7,400 / $42,000) | About 17.6% |
At the billing step in this example, the agreement says to bill the rest of the signed balance, less retainage. The client has paid $28,000, so $14,000 is left. The agreement holds 5% of the signed total, $2,100, until a written closeout step, so $11,900 is due on this bill. The holdback changes when the money is due, not the $34,600 projected cost. See what retainage is.
Spreadsheet or job costing app?
A spreadsheet works if you keep it up as orders, receipts and approvals come in. Give each line the price hit a row: the first budget, the new supplier cost, costs recorded so far, and what you still expect to spend. Use a separate list for proposed and signed client changes, and keep the quote or receipt next to each entry.
In Job Cost Pro, you can take a photo of a purchase receipt and set a job budget. When a purchase receipt names the job or its PO, the app suggests the job; tap once to confirm. Change orders on the job (Pro and up) keep each description and amount. On an open job, compare the costs recorded so far with the budget and see the margin. Keep the cost to finish in your own forecast.
Try Job Cost Pro on an active job. Free plan: 3 active jobs at a time, 50 receipts a month. Free plan available. Some features require a paid plan.
Build a habit for the next quote
Put the supplier quote date and its end date next to the big material lines in your estimate, with the quantities, finishes and lead times you priced. Recheck them with the supplier before you order. On an open job, ask whoever buys materials to flag a new price when it comes in, and save the new quote with the old one.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
What should I do first when a supplier raises a material price?
Get a new written quote for the items and quantities you need. Compare unit prices, freight, tax and delivery dates with the first quote. Ask which prices still apply to orders or deposits you already placed.
Does a material increase change what I put on the invoice?
Check the signed terms and any approved changes. In Job Cost Pro, a fixed-price invoice starts with the contract amount, adds change orders and costs you mark to bill back, and subtracts payments. The written terms decide what goes on this bill.
How should I track retainage?
Keep a separate line for the amount held back. Use the written terms to check the basis, the amount and the release step. Match what is due on this bill and what is held with the unpaid balance, and record payments when they come.
How can I talk with a client about a cheaper material?
Show the specified product and the other one side by side: cost, finish, install needs and delivery date. Put the agreed pick and its effect on scope, price and schedule in writing before you order.
What if I already ordered some of the material?
Check the order confirmation against the new quote and ask which prices apply to what you already ordered. When a deposit or final charge is recorded, it replaces the estimate for that part. Count a deposit only once.