What Is Retainage? How to Track It by Job

A simple log is enough to start. Each time you send a progress bill, write down what was held. Each time a payment or a release notice comes in, update the same job. Check the log against your invoices and your payment records before you decide who to call. If you bill from a construction draw schedule or a schedule of values, the same bill numbers carry into the log.

What retainage means on a job
Say a customer pays progress bills as the work moves along. The agreement says part of each eligible bill is held until a condition is met. On a bill under those terms, show the full billed amount, the amount held back and the regular amount due. Keep the held amount in your job records, so you can follow up when it can be released.
| Open amount | What it means |
|---|---|
| Regular balance | The amount due on the bill after the holdback that you still have not received. |
| Still held | The holdback the customer has not released yet. |
| Released and unpaid | Holdback the customer has confirmed for release, with the payment still to come. |
Say a week ends with less cash in than you billed. The log shows which part is an ordinary short payment and which part is the holdback the terms allow. It also tells you which call to make. A short payment calls for a check against the bill. A holdback calls for a look at the release terms and the papers you need to send.
Set up a retainage log for each job
Start with the agreement and any approved changes that affect billing. Write down who holds the money, which charges the holdback applies to, how it is worked out and what must happen before you can ask for release. Note the billing contact and where you keep copies of invoices, statements and payment records. If a term is not clear, get it in writing before you rely on it in a bill.
- Bill number and date
The invoice number and the day you sent it.
- Billed and held
The bill total before the holdback, the part the holdback applies to, and the amount held.
- Regular amount due and received
The amount due after the holdback, and each payment with its date.
- Release and payment
The amount you asked for, the amount confirmed for release, and the amount paid, with dates.
- Three open amounts
Regular balance, still held, and released and unpaid, each in its own column.
- Proof and next follow-up
Where the invoice, release notice or payment record is saved, and when you will check again.
One bill can carry a regular balance, an amount still held and an amount released and unpaid at the same time. If a bill gets several payments or releases, keep a dated list under that bill number. If a bill was corrected, point to the new copy with a short note on the change. That trail gets you back to the first numbers when a customer statement shows up weeks later.
When you update the log, match the invoice to the customer's payment note and to the money that came in. If one payment covers several bills, use the customer's breakdown to put each amount on the right bill. If a deposit comes in with no breakdown, record it and ask before you apply it. For the bill itself, see how to write a contractor invoice.
Worked example with two progress bills
| Progress bill | Billed | Held (5%) | Regular amount due | Regular payment received | Regular balance |
|---|---|---|---|---|---|
| First bill | $12,000 | $600 | $11,400 | $11,400 | $0 |
| Second bill | $8,000 | $400 | $7,600 | $7,100 | $500 |
| Total | $20,000 | $1,000 | $19,000 | $18,500 | $500 |
At this point the contractor has received $18,500. The $1,500 gap from the $20,000 billed is $500 still due on the second bill plus $1,000 of retainage still held. The $500 stays on the regular follow-up list.
Later the customer confirms release of the full $1,000 and pays $600. The payment note puts that $600 on the first bill's retainage. Two amounts stay open on the second bill: $500 of regular balance and $400 of released retainage.
| Progress bill | Regular balance | Still held | Released and unpaid |
|---|---|---|---|
| First bill | $0 | $0 | $0 |
| Second bill | $500 | $0 | $400 |
| Total | $500 | $0 | $400 |
Cash received is now $19,100 and $900 is still open. When the customer pays the last $500 of regular balance and the $400 of released retainage, and you match both payments to the job, cash received reaches $20,000 and all three open amounts are $0.
Follow the release through to payment
Read the log before you send the next bill, and again as the job gets close to its release conditions. Check your copy of the agreement for the steps it asks for, and contact the person who confirms the release. If they ask for a billing summary, the bill numbers, the amounts held and the holdback still open are already in your log.
- Ask
Write down the amount and the date when you ask for a release.
- Confirm
Update the confirmed amount when you get a reply. If only part is confirmed, leave the rest in the held column.
- Get paid
When the cash comes in, give that payment its own date and reference.
- Save both
The release notice and your record of money received do different jobs, so keep both.
Put a follow-up date next to every open amount. A short note says what you are waiting for, who has it and how much it is. Before you close out the job, check that the amount billed equals the payments received plus any balance still open. Where the numbers do not agree, start with the invoice and the customer's payment breakdown, and fix each difference or leave a clear note on the next step.
Spreadsheet or app
A spreadsheet works well for a simple holdback log. Use a tab for each job, or one table with a job column you can filter. At the top of each job, show three totals: regular balance, retainage still held, and released retainage still unpaid. Link each row to its invoice and papers, so someone else can pick up the follow-up.
Keep the spreadsheet as your retainage log, and keep the job costs in a job costing app next to it. In Job Cost Pro, take a photo of a receipt. When a purchase receipt names the job or its PO, the app suggests the job; tap once to confirm. On an open job, the job shows its cost so far and its margin, and the AI Job Briefing (Pro and up) gives a financial summary. The spreadsheet shows what the customer is holding or still owes. The job costs show what you have spent on the work. For the books side, see contractor bookkeeping.
Start with one job
Pick an open job with a recent progress bill. Enter the billed amount, the amount held and any payment received. Put each open amount in its own column for that bill. Give the row a follow-up date, then do the same for the other bills on that job.
Try Job Cost Pro to keep your receipts together by job. Free plan: 3 active jobs at a time, 50 receipts a month. Free plan available. Some features require a paid plan.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
Is retainage the same as a past-due invoice?
No. Retainage is money held under the job payment terms. A past-due amount is money still unpaid after its due date. Once retainage is released, track it on its own and follow up if it goes past the due date in the terms.
When should I ask for retainage to be released?
Start with the release conditions and timing in the agreement for that job. Write down who to contact and what they need from you. Put a follow-up date in the log so you act once the conditions are met.
How do I record a partial retainage payment?
Log the payment with its amount and date. Apply it to the confirmed release it covers and leave the rest open. If the payment breakdown is not clear, leave it unapplied while you check with the payer. Anything still waiting for release stays in the held column.
Does retainage apply to change orders?
Check the agreement and the approved change order to see if the added work is subject to retainage. Show the eligible amount and the holdback on the invoice, and note the terms in your log.
Can I track retainage for several jobs in one spreadsheet?
Yes. Give each row a job name or number and filter the totals by job. Each job keeps its own billing terms, release records and follow-up contact. A company total is handy; the job rows tell you what to do next.