Cabinet Installer Job Costing for Boxes, Hardware and Labor

A cabinet install can look fine on the quote and tight on money by the last punch-list visit. The cabinet order is easy to see. The extra box of hinges, the delivery charge and the hours spent scribing a filler or driving back for a missing panel are easy to miss. Put those costs on the job while you still know what they were for. To add up one job from its parts, the free job cost calculator shows the price, the profit and the margin.

Set up the job before you order
- Name the job
A short name or number the shop, the supplier and the installers all know. Use it on orders, receipts and time entries.
- Write price and budget apart
The price is what you charge. The cost budget is what you plan to spend.
- Check the cabinet list
Read it against the drawings: boxes, finished ends, fillers and trim. Note who supplies the pulls.
- List the extras
Delivery, carrying boxes upstairs, floor protection, or a return trip after another trade. Each gets its own line.
If the supplier bundles hardware into the cabinet price, write down where that cost sits, so you do not count it twice. When a signed change moves the agreed price, update the price and the cost budget for that work. Keep proposed changes apart until they are signed. See change order tracking.
Track boxes and hardware apart
Keep the supplier invoice with the order. When the cabinets arrive, check the invoice and the delivery list against the boxes. Note what came, what is short and what needs a replacement. A missing panel can mean another order and another trip, even when the box count looks right.
Give hardware its own line: pulls, knobs, hinges, slides, screws and pull-outs. If the crew opens a pack that serves more than one job, record each job's share and make the shares add up to the receipt total, tax included. See how to split one receipt across jobs. If a supplier gives a credit, tie it to the first purchase once the credit is confirmed.
Record install hours by task
Ask installers to log their hours on the job each day, with a short task note. Use the tasks you already talk about on site: unload and protect, set boxes, fit panels and hardware, and punch list. Count the helper's unloading time. Give a return visit its own line, so you can see why the crew went back.
Count every person-hour: two installers working together is two sets of hours. Use your own labor cost rate to turn hours into cost, the same rate in the quote and on the job. Review the hours with the lead before you close the week. Look at hours with no job, work on approved changes, and time spent waiting for access or parts.
Worked example: a fictional cabinet install
| Cost line | Budget | Recorded so far | Cost to finish |
|---|---|---|---|
| Boxes and panels | $4,200 | $4,100 | $0 |
| Hardware | $750 | $680 | $120 |
| Install labor | $2,800 | $2,450 | $400 |
| Delivery and site supplies | $850 | $620 | $80 |
| Total | $8,600 | $7,850 | $600 |
The $2,450 of labor is 49 crew-hours at this example's rate of $50 an hour. The crew expects 8 more hours ($400), plus $120 of hardware and $80 of supplies. $7,850 recorded plus $600 to finish is a projected cost of $8,450, which is $150 under budget.
Both numbers depend on the cost to finish, so update it as bills and hours come in. In the same fictional job, the crew has sent one $6,000 progress bill and the customer held back $600 of it. The $5,400 received, the $600 held and the $6,600 still to bill add up to $12,600. The billing split does not change the $8,450 cost forecast. See what retainage is and how to track it.
Use a spreadsheet or a job costing app
In a spreadsheet, use one row per purchase, credit or time entry, with the job, date, cost line, amount and a note on the receipt or time entry. Keep a totals tab with budget, recorded so far and cost to finish. Have one person check for duplicate receipts and entries with no job before you trust the totals.
In Job Cost Pro, take a photo of the receipt and check what it reads. When a purchase receipt names the job or its PO, the app suggests the job; tap once to confirm. Check the total and the job even when the supplier printed a job reference. Track hours by worker and job, and open the job to see its cost so far and its margin. With a jobsite address and the worker's own login, the iPhone app can show a one-tap clock-in prompt on arrival. Android workers use the clock buttons.
Try Job Cost Pro on your next cabinet install. Free plan: 3 active jobs at a time, 50 receipts a month. Free plan available. Some features require a paid plan.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
What should go in my cabinet cost budget?
Start with boxes and panels, hardware and install labor. Add the delivery, site protection and supplies you expect to pay for. Mark what the customer or another trade supplies, so the budget covers only your scope.
How do I handle a receipt for two cabinet jobs?
Record the share each job used. Keep the receipt and check that the shares add up to its total, with any tax and fees. Use the same job names the crew uses on its time entries.
What if the crew goes back to finish a small item?
Record the return hours on the same job and note why the crew went back. If you expect more visits, put those hours and any parts in your cost to finish.
How can I check margin before the job is done?
Use the agreed price after signed changes. Add the costs recorded so far to the cost still to come. Take that total from the agreed price and divide by the price. Call it projected margin and update it as bills and hours come in.
Where do I track retainage?
If the agreement calls for it, track the amount held and the release status next to the progress bill. Keep the release condition and a follow-up date with the bill, and record the payment when it comes.