Construction Draw Schedule (Filled-In Sample)
This post is for the contractor sending the bills, with or without a bank in the middle. Most of what you find on this search is written for the homeowner's loan. I wanted the other side: a schedule with every dollar filled in, where each number comes from somewhere you can check. Each draw below becomes its own bill, and the free contractor invoice template has the deposit and balance lines already built in.
Everything here is one worked example. Your percentages should come from your own costs and your own contract, and the legal points (deposits, waivers, retainage) depend on your state. Check those with your attorney.
What a draw schedule is (and what it is not)
A draw schedule is the payment plan inside your contract. Each payment, or draw, is tied to a piece of work the client can see is finished: demo and rough-in passed, drywall up, cabinets set. When the milestone is done and checked, you bill that draw.
It is also not the same as a schedule of values. A schedule of values breaks the contract into line items by trade or phase, often for a lender or a commercial owner. A draw schedule says when you get paid. On a small residential job you may only need the draw schedule. On a bank-financed job, the lender has its own draw process, and your schedule has to fit it.
A sample draw schedule for a $55,000 remodel
Here is the example: a fixed-price kitchen and bath remodel, $55,000, five draws. The percentages are mine for this job, not a rule.
| Draw | Milestone (finished and checked) | % | Amount | Billed to date |
|---|---|---|---|---|
| 1 | Deposit at signing | 10% | $5,500 | $5,500 |
| 2 | Demo and rough-in passed | 25% | $13,750 | $19,250 |
| 3 | Drywall finished | 25% | $13,750 | $33,000 |
| 4 | Cabinets and counters set | 25% | $13,750 | $46,750 |
| 5 | Final walkthrough, punch list done | 15% | $8,250 | $55,000 |
Notice what each milestone has in common: a client can walk the job and see it. Nobody argues about whether drywall is finished. That is the point. A milestone you have to explain is a draw you will wait on.
Where the $55,000 came from
A draw schedule is only as good as the price under it, so here is the price. I ran the cost side through the job cost calculator: 320 labor hours at $45, $18,500 in materials, $9,800 in subs and $1,300 other comes to $44,000. At a 25% markup that prices the job at $55,000, with $11,000 of gross profit, a 20.0% gross margin.
That 20.0% is not all yours. It has to pay the office, the truck and the insurance before anything is profit. The overhead and profit calculator splits it: at 12% overhead and 10% profit, $44,000 of cost prices at $55,000 again ($44,000 x 1.10 / 0.88). Of the $11,000, $6,600 is overhead and $4,400 is profit, which is 8.0% of the price.
| Line | Amount |
|---|---|
| Labor: 320 hours x $45 | $14,400 |
| Materials | $18,500 |
| Subcontractors | $9,800 |
| Other (permits, dump, rental) | $1,300 |
| Total cost | $44,000 |
| Overhead (12% of price) | $6,600 |
| Profit (10% of cost) | $4,400 |
| Contract price | $55,000 |
Keep billed-to-date ahead of cost-to-date
Here is the rule I care about most: at every draw, the money you have billed should be ahead of the money you have spent. If it is not, you are lending the client your cash and funding their job. This table puts the schedule next to the planned cost at each point.
| After draw | Billed to date | Cost to date (planned) | Cash ahead |
|---|---|---|---|
| 1 | $5,500 | $0 | +$5,500 |
| 2 | $19,250 | $14,000 | +$5,250 |
| 3 | $33,000 | $26,500 | +$6,500 |
| 4 | $46,750 | $39,000 | +$7,750 |
| 5 | $55,000 | $44,000 | +$11,000 |
Now the mistake I see most. Say the cabinet supplier wants a $10,000 deposit before draw 3, and you pay it out of pocket. Cost to date jumps to $36,500 while you have billed $33,000. Cash ahead is now -$3,500. You are funding the job until drywall is done. The fix is in the schedule, not the bank account: tie a draw to the cabinet order, or make the deposit big enough to cover the early buys.
The only way to know where you stand is to know your cost to date before you send each draw. That is just job costing done while the job runs; there is more on it in track job profitability while it runs.
Turning each draw into an invoice
Every draw gets its own invoice with its own number. Do not send one invoice and keep editing it. Each draw invoice should show the whole picture so the client never has to add anything up. Here is draw 3:
| Invoice line | Amount |
|---|---|
| Contract total | $55,000 |
| Billed before (deposit + draw 2) | $19,250 |
| This draw: drywall finished (25%) | $13,750 |
| Billed to date | $33,000 |
| Contract balance left | $22,000 |
The steps for the rest of the invoice (your info, the client, terms, the due date) are in how to write a contractor invoice.
- Every milestone is something the client can see is finished
- No draw is tied only to a date
- The deposit covers the early buys, or a draw is tied to them
- Each draw gets its own invoice number
- Change orders are billed on their own, outside the schedule
- If the job uses lien waivers, you know when each one is asked for or given
Change orders, lien waivers and retainage
Change orders sit outside the draw schedule. An approved change gets its own line or its own invoice, so the original schedule still adds to the original contract. The habit that makes this work is to track change orders in writing as they happen.
Lien waivers are often asked for at each draw on jobs that use them: you sign one for the money you received, and you may collect them from your subs too. The basics are in the post on lien waivers. The forms and the rules are set by each state, so get the right one from your attorney.
Retainage is money the client holds back from each draw until the end. Some jobs use it and many small residential jobs do not. The rules and the amounts vary by state and by contract, so I am not giving you a number here. If a contract has it, plan your cash for the wait.
Fixed-price vs cost-plus draws
Everything above is a fixed-price job: each draw is a percent of a set contract price. A cost-plus job draws differently. Each draw is the cost you have actually spent and can show, plus your agreed fee. The schedule follows the receipts, not a percent. The difference between the two contract types is laid out in fixed-price vs cost-plus contracts, and the billing side has its own page on cost-plus invoicing.
Where the app fits (honest limits)
A draw schedule asks one question at every milestone: what has this job cost so far? I built Job Cost Pro to answer that one. You photograph receipts and the AI reads the line items (when the receipt names the job or you scan at the jobsite, it suggests that job for one tap to confirm), and the crew clocks in so hours land on the job. Before you send a draw, the cost to date is already there, from costs recorded so far. An invoice starts from the job (the contract, signed change orders, payments and the costs you mark to bill back), and you review it before it goes out. It does not build a draw schedule for you; you set the milestones. It is not a scheduling tool. Free on the App Store: 3 jobs, 50 receipts a month, AI scanning included, no card. Get it here.
Whatever you use, set the draws before the job starts and check cost to date before every bill. That one habit keeps you from paying for somebody else's kitchen.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
How many draws should a construction job have?
There is no set number. Use one draw for each milestone a client can see is finished, plus the deposit and the final. More draws keep your cash closer to your costs; fewer draws are simpler for the client. The example in this post uses five on a $55,000 job.
What percentage should a contractor deposit be?
There is no single answer. It should cover the early buys and your first weeks of cost, and some states limit how much a contractor can take up front on home improvement work. Check the rule in your state with your attorney before you write the deposit into a contract.
What is the difference between a draw schedule and a schedule of values?
A schedule of values breaks the contract price into line items by trade or phase. A draw schedule says when each payment is due, tied to finished milestones. Lenders and commercial owners often want both; a small residential job may only need the draw schedule.
Can I bill a draw before the milestone is finished?
Only if the contract says so. A draw tied to a milestone is billed when that milestone is finished and checked. Billing early invites a dispute. If you need cash sooner, change the schedule before the contract is signed, for example by tying a draw to a big material order.
What is the difference between progress billing and a draw schedule?
Progress billing means you bill as the work moves forward instead of all at the end. A draw schedule is one way to do it: set payments tied to finished milestones, agreed in the contract. Commercial jobs often bill by the percent of each line item that is done, on a schedule of values. Most small residential jobs run on a draw schedule.
How do change orders affect the draw schedule?
They sit outside it. An approved change order is billed on its own line or its own invoice, so the original draws still add up to the original contract price. Get each change approved in writing before the work, and bill it when the changed work is done.