Fence Contractor Job Costing for Materials and Crew Time

A fence quote starts with the run, the height, the style and the gates. Job costing starts with the same details, then adds what you really buy and the hours your crew really works. When the quote and the job record use the same lines, you can see where a cost moved and check why. To price one job from its parts, the free job cost calculator shows the price, the profit and the margin.

Set up the job before you order
- Name the job
A short name your crew and supplier know. Put that same name on orders, receipts and time entries.
- Five budget lines
Posts and hardware, panels and gates, concrete and gravel, crew labor, and hauling or disposal.
- Count the posts
Corner, end and gate posts apart if they use different parts.
- Write the scope
Who removes the old fence, what the gate setup includes, and how spoil and debris are handled.
Keep the lines broad enough that the person entering a receipt knows where it goes. Keep your quantity list with the job, so you can compare the order with what showed up and what went into the ground.
Track posts, panels and concrete by job
Keep three things apart when material comes in: what you ordered, what the supplier charged and what you returned. Your post count checks the delivery, the supplier receipt is the recorded cost, and the return receipt is the credit. A missing panel, an extra bag of concrete or a return still in the truck can put those out of step.
Record the supplier, date, job, line and amount with each purchase. If a truckload serves two jobs, record each job's share once, from the line items, and keep the receipt. See how to split one receipt across jobs. Link a return credit to the same job and line as the purchase, and keep a planned return apart until you have the store's record.
Count crew time and site extras
Record crew hours by person and job. If the crew leaves one address for another, split the time, so the first fence carries only its own labor. Multiply the hours by the labor cost rate you use for that person, and keep the same method in the budget and on the job. Note what drove extra time: buried material, tight access, or waiting on a delivery.
At the end of the week, look for receipts with no job, shifts with no job, and supplier charges that came in but are not entered yet. List the work left to do on its own. Keep proposed extras apart from approved scope, and keep the contract amount, amounts billed and payments received in their own fields. See change order tracking.
Worked example for a fictional fence job
| Cost line | Planned | Recorded so far |
|---|---|---|
| Posts and hardware | $550 | $600 |
| Panels and gate, before the return credit | $1,700 | $1,845 |
| Concrete and gravel | $350 | $415 |
| Returned panels credited to this job | $0 | -$160 |
| Crew labor | $1,540 (44 hours x $35) | $1,680 (48 hours x $35) |
| Hauling and disposal | $210 | $225 |
| Total direct job costs | $4,350 | $4,605 |
Posts, panels and concrete add up to $2,860 before the $160 return credit, so net materials are $2,700 against a $2,600 budget. The costs for both scopes are $255 over the first budget. Give the added removal its own budget if you want to compare the two scopes.
That is a snapshot while the job is open; add the work left and bills not yet in for the margin at the finish. Company overhead is outside this example. On the payment side, say the full $7,900 is billed and the agreement holds $395 until its release conditions are met: $7,505 received plus $395 held is $7,900. The job cost is still $4,605. See what retainage is.
Spreadsheet or app?
A spreadsheet works when you keep it current. Give each purchase, credit or time entry its own row, with the date, job, line, amount and a reference to the paper behind it. Keep estimates, approved changes, invoices and payments on a separate sheet, with the same job name.
An app helps when receipts and hours come from several people. Job Cost Pro reads a receipt photo. When a purchase receipt names the job or its PO, the app suggests the job; tap once to confirm. Labor by job shows the job labor so far against its labor budget. On iPhone, a worker with their own login gets a one-tap prompt to clock in on arrival and to clock out when leaving a jobsite with an address. On Contractor and up, the owner can turn on automatic clock-in for a worker, and the worker agrees in the iPhone app; it only happens between 6 a.m. and 8 p.m. in the owner's payroll time zone.
Try Job Cost Pro on your next fence job. Free plan: 3 active jobs at a time, 50 receipts a month. Free plan available. Some features require a paid plan.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
What should I record for posts, panels and concrete?
Track each as its own budget and cost line if that is how you quote the job. Include hardware, gate parts and gravel in the lines your crew uses, and keep the receipt.
How do I cost a supply run for two fence jobs?
Use the receipt lines to give each job its share. Check that the two shares add up to the cost, and record any later credit on the job that had the cost.
Do I use total crew time or each worker’s hours?
Each worker’s hours on that job, at the labor cost rate for that person, then add them. That explains the total if the crew changed during the job.
What is the difference between job margin and cash received?
Margin here is the agreed price less the costs recorded so far, divided by the price. Cash received is money that has arrived. Keep unpaid and held amounts in the billing records.
How do I track retainage on a fence job?
Use the terms in that agreement. Record the amount billed, received and held, and the release conditions, apart. Keep a follow-up note and record the last payment when it comes.