Siding and Gutter Job Costing by House

A crew can finish the siding at one house, hang gutters at a second and buy supplies for both on the same trip. The supplier sends one receipt. The crew turns in one day of hours. If all of it goes under one address, the weekly total still adds up, but the siding and gutter costs end up on the wrong house. To add up one job from its parts, the free job cost calculator shows the price, the profit and the margin.

Set up one cost sheet per house
- Name the house
An address or short job name the office and crew know. If the builder uses lot numbers, add the street or subdivision.
- Price and budget
Start with the agreed price and the budget from your quote.
- Five cost lines
Siding materials, siding labor, gutter materials, gutter labor, and shared costs for the whole house.
- Scope notes
What the quote covers, with allowances and unsure work on their own lines.
Siding can include trim, fasteners, removal and disposal as well as the panels. Gutters can include downspouts, outlets, hangers and end caps as well as the runs. Keep the first budget in view and add a note when the scope changes. If you find damaged sheathing after tear-off, price the new scope and track the work once it is approved. See change order tracking.
Track materials, labor and shared costs
Materials. Give the supplier the job name when you order. When the invoice comes, check the quantities, freight and other charges against the order. If one receipt covers two houses, put each item on the house that used it and keep a reference to the receipt. See how to split one receipt across jobs. Apply a store credit to the house that carried the returned items.
Labor. Record the worker, date, house and work. A day with siding at one house and gutters at another is two entries. If both trades work one house, give each trade its own time entry. Turn hours into cost the same way in the quote and on the job, and count paid setup, removal and cleanup in the work they belong to. If a sub does the gutters, record the bill on the gutter lines.
Review the job while it is open
Pick a set time to compare the budget with the costs recorded so far. First, look for bills, credits and hours that have not come in. Then look at the biggest gaps by line. If siding labor is over, check for extra tear-off, a return visit, or time logged under the wrong address. Write down the cause before you change the next quote.
Keep a list of costs you expect but have not recorded, like a gutter bill or a last day of labor. Company overhead, unfinished work and bills not yet in all change what that number means. Keep billing and collections on their own lines: what you billed, what the customer paid and what is still open. If the terms call for retainage, record how much was held on each bill and what the agreement asks for before release. See what retainage is and how to track it.
Fictional worked example for one house
| Direct cost | First budget | Recorded so far |
|---|---|---|
| Siding materials and trim | $4,800 | $5,150 |
| Gutter and downspout materials | $1,800 | $1,650 |
| Siding crew labor | $3,600 | $3,850 |
| Gutter crew labor | $1,400 | $1,250 |
| Shared access, haul-off and delivery | $1,400 | $1,350 |
| Total | $13,000 | $13,250 |
The siding materials line is $5,400 of purchases less a $250 store credit. The job has $250 more direct cost recorded than the first budget. The owner can look at the change order and the crew records to see how much of that came from the sheathing work. $19,200 less $13,250 is $5,950, about 31.0% of the price on the direct costs recorded so far. The job is still open, and the example leaves out company overhead.
The same fictional job holds back 5% of a $12,000 progress bill: $600 held and $11,400 payable. If the builder pays $10,000, record $1,400 still due on the bill and $600 held on its own line. Another $7,200 of the price is not billed yet. $10,000 received, $1,400 due, $600 held and $7,200 not billed add up to $19,200.
Spreadsheet or job costing app?
A spreadsheet works if someone owns the updates. Use a tab for each house, with columns for the date, job, line, item, cost and the paper behind it. If several people send you receipts and hours, agree on how they label them, and on who checks that each amount is on the right house.
In Job Cost Pro, take a photo of a receipt. When a purchase receipt names the job or its PO, the app suggests the job; tap once to confirm. When one receipt covers two houses, split it by line item to the jobs that used them (receipt splitting is Pro and up). Crew hours go on the job they belong to. In the iPhone app, workers with their own logins can tap the prompt to clock in when they arrive at a jobsite with an address set.
Try Job Cost Pro on your next house. Free plan: 3 active jobs at a time, 50 receipts a month. Free plan available. Some features require a paid plan.
Track your next job with Job Cost Pro
Scan receipts, confirm the suggested job, and see your recorded costs against your budget. Start with the free plan in your browser or get the iPhone app.
Google Play: US only.
Free plan available. Some features require a paid plan.
FAQ
Should I track siding and gutters apart on one contract?
Yes. Keep one record for the house and separate lines for each trade material and labor. Keep shared costs in view, so you can compare each trade with its budget and still see the house total.
How should I handle a receipt for two houses?
Put each item on the house that used it. If a charge covers both, use the same split method every time and note why. Check that the two shares equal the charge, and keep the receipt.
Where does repair work outside the first scope go?
Describe the change and keep its price and approval with the job. Record the labor and materials on that house when they happen. Keep the first budget, so you can explain the change later.
Does retainage change what the job cost?
No. Retainage is part of a bill held under the job terms. Track it with billing and collections. Your cost records still show the materials, labor and other costs you recorded.
When can I use these numbers to price the next house?
Once the last bills, credits and hours are in. Note what was special about that house before you copy any of its numbers into the next quote.